NYSDOT

MP Engineers’ (MPE) responsibilities for this project included preparation of all required MPT drawings, including general notes as required to support the Client’s permit applications for a construction of duct banks in...

This project involved a complete replacement of signing and lighting systems (including all under deck lighting) along the entire Cross Bronx Expressway (CBE) corridor. The CBE is approximately an 11 mile 6 lane (3 lanes in each dir...

MP Engineers was retained to design a load transfer and a jacking procedure for seven structural load-bearing columns (four concrete and three brick), and parts of a load bearing basement wall in a multi-story apartment building loc...

This project involved replacing deteriorated concrete bridge deck slabs, repairing deck spalls, repairing and reconstructing deck joints, repairing headers, removing asphalt surfacing, placing new membrane waterproofing and resurfac...

Under this project, the Port Authority of New York and New Jersey proposed to repair and rehabilitate the GW Bridge approaches and sidewalks in the main span.    MP Engineers, P.C. inspected the NJ Approaches over th...